    naughty boy

    Project 5 weeks behind...
    Contract due to end in a week..

    I'm called into the directors office who is disppointed that the system isn't finished and the things wasn't flagged. I gotta hold my hands up and blame changing user specs and the beauty of agile programming philosophy...

    feel disappointed myself ...

    Ended up with 5 weeks extension to finish the thing off... would have preferrred longer

    Maybe if i turn it around i can still come out of this the hero?
    --------------------------------------------------------------------------------

    SA - Is it like a dragons nostril?

    #2
    Dont worry about coming out as a hero you get no money for that. Mess up the project a bit more and next 5 weeks are sorted

    Comment


      #3
      Didn't you have a solid change control process?? this is a classic mistake developers make, if a user ask for changes they just go a head and do it without documenting the impact on their time schedule and overall project delivery.

      if you follow a proper change control process you'll have a documentation and evidence of the changes users asked for and their impact on each aspect of the project (inc the project plan/ delivery deadlines) well ahead of time!! convince your boss that this is needed, how can you guarantee that today by 4 pm the users will not ask for more drastic changes?? of course changes are always in your benefit cuz it means you have a business case to extend the deadlines leading to extending your contract !! Good practice PAYS

      Comment


        #4
        to be honest i have learnt a lot from this recent debacle.... cover your back...
        --------------------------------------------------------------------------------

        SA - Is it like a dragons nostril?

        Comment


          #5
          Originally posted by kramer
          Project 5 weeks behind...
          Contract due to end in a week..

          I'm called into the directors office who is disppointed that the system isn't finished and the things wasn't flagged. I gotta hold my hands up and blame changing user specs and the beauty of agile programming philosophy...

          feel disappointed myself ...

          Ended up with 5 weeks extension to finish the thing off... would have preferrred longer

          Maybe if i turn it around i can still come out of this the hero?
          What happened to your weekly progress reports?
          "A people that elect corrupt politicians, imposters, thieves and traitors are not victims, but accomplices," George Orwell

          Comment


            #6
            Originally posted by Paddy
            What happened to your weekly progress reports?
            This is a good point.
            Rule #76: No excuses. Play like a champion.

            Comment


              #7
              monthly reports...

              My estimates were just rubbish too.. as I was given the BA role but didn't know the business which led to badly conceived guestimates.
              --------------------------------------------------------------------------------

              SA - Is it like a dragons nostril?

              Comment


                #8
                easy mistakes to make!

                i have found that because the project team often have other jobs to do as well the project work is often not seen as a main proirity - it gets looked at 2 days before the deadline and then it is realised that it will take 2 weeks to do this 'easy' bit of work

                weekly reviews!!!!!!

                Comment


                  #9
                  "Maybe if i turn it around i can still come out of this the hero?"

                  Maybe if Superman had charged 600 quid a day he would of got Lois Lane!
                  What happens in General, stays in General.
                  You know what they say about assumptions!

                  Comment


                    #10
                    What happened to your tolerance ?